15 February
Inventory submission due by Parties.
15 Feb - 15 March
Initial data checking for timeliness, format, completeness and consistency (CEIP). Bilateral discussions with Parties.
March
Extended EMEP Bureau meeting (2-4 March)
Stage 1 review. Country reports launched by 30 March
15 March
Re-submission deadline (if applicable) by Parties to be included in the UNECE/EMEP database and in the modelling assessments for that year.
April
Draft expert estimates for modelers (16 April)
May
10-11 May: Annual TFEIP/EIONET joint meeting, Cyprus
12 May: Joint workshop with the TFMM
Review process Stage 2.
Launch of password-protected web site with country specific review results and questions (31 May).
June
Parties provide comments to stage 1 and 2 review findings.
Annual update of WebDab.
CEIP document for SB on Present State of Emission Data. (15 June)
Stage 3 centralised review (21-25 June 2010, likely in Copenhagen at EEA premises).
30 July
Manuscript of Review report 2009 to EMEP Steering Body
August
Data and Status report submitted to EMEP Steering Body for endorsement.
September
EMEP Steering Body meeting (7-9 Sept)
December
Data and Status report (including results of review process) submitted to Executive Body for approval.
EMEP Executive Body meeting
Update of webdab with late submissions